OML 100 Fire Water Upgrade (2010)

Project Details

OML 100 Fire Water Upgrade (2010)

Client: Total Exploration and Production Nigeria Limited

Location: Port Harcourt

Cakasa (CESL) carried out Detailed Engineering Design (DED) on the modification of the existing Firewater Network System – Piping works.

The modification involved provision of 2 new Fire Water Pumps with capacity of 1200m3 /hr – 1 each @ ODP1 (Wellhead Platform) & ODD1 (Processing Platform), construction of a Platform extension (pancake module) – @ ODD1 and the extension of the existing Deluge System (to cover new equipment), upgrade of the Fire Water components (e.g. Hydrants), provision of 1 additional Jockey Pump with capacity of 30 m3/hr @ ODD1 and relocation of a Gas Manifold @ ODD1.

Structural Activities

E & I Activities

ceslOML 100 Fire Water Upgrade (2010)